Kumasi to experience Dumsor till the end of the year, ECG announces affected areas

Major parts of the Kumasi Metropolis will be experiencing intermittent power supply till December 2021 the Electricity Company of Ghana has announced.

Kwame Agyemang Budu, the managing director ECG said these power outages is a result of the ongoing construction of a 330kV transmission line expected to be completed by December 2021 with some affected areas being KMA, Asokwa, Oforikom, Ejisu, and other MMDAs close to Kumasi.

“From Kintampo to Tamale and Tamale to Bolgatanga, those two areas have been completed. They are yet to complete the last phase which is from Kumasi to Kintampo and by the end of the year, we should have a full 330KV transmission line from Kumasi all the way to the North.” He said.

Mr Agyemang during a press briefing on Tuesday attributed the power challenges to the overloading of GRIDCo’s 161KV transmission line and Bui dam’s shutdown, leading to low voltages to parts of the country that receive power from Abomaso.

READ ON  ECOWAS Chairman, Akufo-Addo demands release of Guinea’s overthrown president
Advertisements

He indicated that constructing this 330KV transmission line will help offload some of the congestion on the 161kV line and added that the government’s decision to relocate the Ameri plant to the Ashanti Region to also help solve the issue.

“All our power generators are all the way in the south and power going to the north goes through Kumasi so by the time the power gets here (Kumasi) losses are incurred, voltages are reduced so they want to establish a plant here so that power going to the north will not be a problem and it will not affect the Ashanti region as a whole.

“The problem here in the Ashanti region is system challenges whereby the 161kV transmission line is overloaded. That is why we are having all these problems. We do not have a timetable for these power outages. This is because we have not gotten to that level.

READ ON  Multimedia, CEO sue Ken Agyapong for defamation

GRIDCo supplies us with power and they have not stated that there is no power. There is power but their line is just congested and all they need to do is to upgrade it.

Advertisements

“We are also strengthening the existing networks to help evacuate more power. Our short term measures are within a three to six months time frame. We are replacing our multi-jointed cable from Anyomaso to Boadi and from Boadi to Kassi”. He explained.

WhatsApp & Telegram Job Alert

To get daily Job Alerts on Whatsapp, Join Our WhatsApp Group via the link below.

NOTE: PLEASE IF YOU’RE ON ANY OF OUR WHATSAPP GROUPS, DON’T JOIN THIS ONE

CLICK HERE TO JOIN WHATSAPP GROUP

Advertisements

CLICK HERE TO JOIN TELEGRAM CHANNEL

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button